The Scotsman

Crumbling concrete forces repairs to 133 sections of Edinburgh’s tram line

- By ALASTAIR DALTON alastair.dalton@scotsman.com

Repairs have had to be made to 133 sections of Edinburgh’s tram line after concrete that should have lasted 50 years has crumbled under the weight of buses.

Damage totalling 40m long on Princes Street and other roads is being fixed by contractor Bilfinger, which built the route that opened just seven years ago.

The company is completing the work at its own undisclose­d expense after Edinburgh Trams said the firm had admitted liability for the faults, which were caused during constructi­on.

It has forced a series of overnight closures of city centre streets, including parts of Princes Street and Shandwick Place this week, although there has been no planned tram disruption.

City council Conservati­ve group leader Iain Whyte said the news “begs lots of questions” over whether other defects remained.

The full extent of the problem comes two days after The Scotsman revealed Edinburgh Trams had ordered safety repairs after the "concrete form” defects became “degraded”.

The city council-owned company said the damaged areas were limited to “where there is heavy bus traffic”. It said these were “at constructi­on joints where the track is present”.

An Edinburgh Trams spokespers­on said: “The expected life span is 50 years and that remains the case.

"These are constructi­on

defects, hence the liability for the repairs falling to the contractor.

"The maintenanc­e contractor is meeting the cost obligation­s for this work."

However, its cost was "commercial­ly sensitive”.

The spokespers­on said: “Providing there are suitable weather conditions, the works will be completed this weekend.

“Of the approximat­e 5,500m of on-street track, 133 defects were identified.

"With each defect being approximat­ely 0.3m in length on average, this represents 0.73 per cent of the on-street track length.”

Edinburgh Trams said track sealant, which protects the road from any stray electric current from the trams, had been replaced at the

same time. It said: “To minimise renewal costs, we have been monitoring the sealant to maximise its five-year life span.

"We are replacing that on a condition-based approach and the new product we are using has a ten-year lifespan.”

Edinburgh Trams declined to say how much that work had cost but said it was “part of a planned renewals programme as agreed with the council”.

Mr Whyte said: “These defects show once again the problems with tram constructi­on in Edinburgh are never ending.

"The saving grace on this occasion is at least the contractor, rather than the taxpayer, is footing the bill.

“That doesn’t take away from the disruption caused and begs lots of questions as to whether there are any other defects still out there.

"Or whether the lessons have been learned in signing off work under the current tram constructi­on [extending the line to Newhaven].

“All the time, the costs to the taxpayer of the tram fiasco continue to rise.”

 ?? ?? Damage is being fixed by contractor Bilfinger, which built the route that opened seven years ago.
Damage is being fixed by contractor Bilfinger, which built the route that opened seven years ago.

Newspapers in English

Newspapers from United Kingdom