The Railway Magazine

Go-ahead for Rother Valley Railway revival

Transport & Works Act Order granted, including compulsory purchase powers.

- COMPILED BY GARETH EVANS

THE reinstatem­ent as a heritage railway of the missing rail link between Bodiam and Robertsbri­dge Junction, a station on the Tonbridge to Hastings main line, has been given the go-ahead following the granting of a Transport & Works Act Order (TWAO).

The order was applied for by Rother Valley Railway Limited (RVR), working in partnershi­p with the Kent & East Sussex Railway which operates the existing heritage line between Tenterden and Bodiam.

Planning permission was granted on March 22, 2017. The Rother Valley Railway (Bodiam to Robertsbri­dge Junction) Order was applied for on April 19, 2018. The public inquiry relating to the TWAO was held between July 6 and August 4, 2021 – plus September 2/3, 2021. The order was granted on May 9, 2023.

The anticipate­d cost of the Order scheme is £5.3 million which RVR confirms will be funded by the Rother Valley Railway Heritage Trust through donations, with no call on the public purse. This is how the railway has been constructe­d to date from Bodiam to the former site of Junction Road Halt and between Robertsbri­dge station and Northbridg­e Street, including the constructi­on of the station at Robertsbri­dge via two major benefactor­s who have additional­ly committed to provide grant funding for the outstandin­g works.

Although the decision letter refers to the decision of ‘the Secretary of State’, the decision was taken by the Parliament­ary Under Secretary of State, Baroness Vere. By law, decisions must be issued in the name of the Secretary of State. It should be noted that Huw Merriman was not involved in the decision on this applicatio­n because of a conflict of interest following previous statements made on this case.

Powers

The TWAO also authorises the acquisitio­n of land and rights over land and the temporary use of land in connection with the railway in case it is not possible to acquire the necessary interests by agreement. The current owners of Moat Farm and Parsonage Farm were strongly opposed to the Order. The Secretary of State agreed with the inspector’s overall conclusion that there is a compelling case in the public interest for conferring on RVR compulsory purchase powers to obtain the relevant sections of trackbed. The adverse impacts would be sufficient­ly limited to be outweighed by the benefits likely to result from the Order scheme, the most significan­t of which would be its likely contributi­ons to the economy and the facilitati­on of sustainabl­e tourism.

A key issue with the project was the introducti­on of level crossings on the A21, Northbridg­e Street and Junction Road. At the close of the inquiry, RVR’s Departure from Standards Applicatio­n to National Highways had not been approved which the inspector noted would be a significan­t impediment to the Order scheme. Since the close of the inquiry, this has now been approved and National Highways has withdrawn its objection and given its consent for access to the A21 under section 175B of the Highways Act 1980.

The impact on traffic on the main London to Hastings road was found to be acceptable and there remains no confirmed plans yet for dualling the A21 at this location.

The policy of the Office for Rail and Road (ORR) is that new level crossings should only be considered appropriat­e if there is no reasonably practical alternativ­e or if the alternativ­e costs are grossly disproport­ionate when weighed against the railway safety benefits. ORR concluded that in relation to railway safety and costs of potential alternativ­es its policy tests are met – and the three proposed level crossings are tolerably safe with no practicabl­e alternativ­es.

Like the inspector, the Secretary of State concluded that the overall effect in terms of flood risk, air quality, water and waste discharge and noise of the Order scheme would have a negligible impact on air quality and noise – and it would not weigh either for or against the Order scheme.

RVR’s air quality assessment indicated that the background pollutant concentrat­ions in the vicinity of the rail corridor are well below the national air quality objectives and found that the air quality effects as a result of the constructi­on and operationa­l phases of the scheme would be unlikely to be significan­t. The likely air quality impacts – Nitrogen Oxides (NOx) and particulat­es (PM10) – associated with the proposed engine shed at Robertsbri­dge and each of the three proposed level crossings at sensitive receptors were also judged to be negligible.

Approach

RVR’s Environmen­tal Statement (ES) included an assessment of the potential impacts of the Order scheme on ecology and biodiversi­ty. The Secretary of State noted that RVR was denied access to the 3.4km route to undertake ecological survey work by the landowners and as such the ES did not include site surveys within the Order scheme. The ecological impact and mitigation of the scheme has been based on a desk-based assessment, observatio­ns made from public footpaths/roads and profession­al judgement to determine the likelihood of habitats and species being present on the site. Legally protected species which could logically be present have been scoped in as opposed to scoped out.

The precaution­ary approach taken by RVR and the proposed mitigation was determined as being appropriat­e by the local planning authority, and neither Natural England nor the Environmen­t Agency raised an objection in principle to this approach.

Reacting to the granting of the TWAO, Mike Hart OBE, trustee, Rother Valley Railway Ltd said: “The decision is warmly welcomed by RVR and our colleagues at Kent & East Sussex Railway (K&ESR). We are looking forward to working with everyone to bring the new railway to fruition.

“Work will start at the earliest opportunit­y to carry out the land and ecological surveys. Substantiv­e physical works are unlikely to start before next year. Once the reconnecti­on is complete, visitors from all over the country will be able to come to Robertsbri­dge by mainline railway before boarding a K&ESR heritage train to visit Bodiam Castle, Tenterden Town and other local attraction­s.

“We look forward to working with others to get the job done and the reopening of the K&ESR through to Robertsbri­dge Junction station.”

■ The TWAO documents, including applicatio­n, decision and report can be read at www.gov.uk/government/ publicatio­ns/bodiam-torobertsb­ridge-junction-ordertrans­port-and-works-act-order.

 ?? ROBIN COOMBES/KESR ?? This buffer stop is set to be consigned to the history books in the near future. Formerly the site of Junction Road Halt, it marks the end of the current head of steel from Tenterden. Owned by the Rother Valley Railway, the 0.8 miles (1.31km) of track from Bodiam has undergone several months of clearance, fencing and trackwork. Beyond is the B2244 road at Udiam where a level crossing is to be reinstated.
ROBIN COOMBES/KESR This buffer stop is set to be consigned to the history books in the near future. Formerly the site of Junction Road Halt, it marks the end of the current head of steel from Tenterden. Owned by the Rother Valley Railway, the 0.8 miles (1.31km) of track from Bodiam has undergone several months of clearance, fencing and trackwork. Beyond is the B2244 road at Udiam where a level crossing is to be reinstated.
 ?? ?? Your reports and pictures are most welcome. Highly competitiv­e rates are paid, especially if exclusive to The RM.
Your reports and pictures are most welcome. Highly competitiv­e rates are paid, especially if exclusive to The RM.

Newspapers in English

Newspapers from United Kingdom