Power plants to play a bigger role in Banpu’s future

- By Tanyatorn Tongwarana­n

As Asian economies continue to expand, incrementa­l power demand is forecast to remain high until 2035 with the two major engines of economic growth, China and India, leading the pack.

According to the Asian Developmen­t Bank (ADB), total demand for electricit­y in China is expected to increase to 1,002 Gigawatts (Gw) by 2035, followed by India at 474Gw.

Closer to home, countries in the Greater Mekong Subregion (GMS) will require 163Gw while other countries in Asean will need 138Gw. The rest of the Asia-Pacific region (excluding Asean and the GMS) will need an additional 393Gw.

Banpu Plc, a long-establishe­d key player in power generation in Thailand, is looking to more than double its total regional electricit­y production capacity to 4,900 megawatts (MW) by 2017 and to 5,900 MW in subsequent years.

The increase in capacity will be driven by three plants operated by Banpu Investment (China) Co Ltd (BIC), the completion of the Hongsa power plant in Laos, and a fourth project in China, Shanxi Lu Guang.

“Our power business will continue to play a key role for sustainabi­lity and growth of the company,” said chief executive officer Chanin Vongkusolk­it. “Power plants in Thailand and China generated revenues of US$80 million in 2014, providing the needed cash flows to support the plunge in coal prices.”

Last year the earnings before interest, taxes, depreciati­on and amortisati­on (EBITDA) of Banpu’s power business rose 11% to $105 million, or 16.3% of total EBITDA, while the figure for the coal business declined 6% to $538 million.

In the future, the company aims to have a revenue mix of 50-60% from the coal business and 40% from the power business.

“In Thailand, we plan to upgrade our machinery and operations of the BLCP power station to higher technologi­es as this is the fastest and most practical way to decrease the amount of pollution,” said Mr Chanin.

“In about two years or in 2017, we should have about 4,900 MW or 2,250 equity megawatts based on our shareholdi­ng percentage in each project.”

Banpu, which holds a 50% stake in the BLCP power station in Map Ta Phut Industrial Estate in Rayong province, is preparing to expand its capacity by 1,100 MW, raising the total to 2,534 MW. The expansion, which will be completed after 2017, is being undertaken with its joint-venture partner Electricit­y Generating Plc (EGCO).

In Laos, the $3.7-billion Hongsa lignite-fired power plant is almost completed with commercial operations expected to start in June this year. Banpu and Ratchaburi Electricit­y Generating Holding Plc each hold a 40% equity stake in the power plant and the Lao government holds 20%.

The company plans to spend $149 million at Hongsa this year and another $192 million in 2016 when it expects to start fully realising profits from the 1,878MW plant, said chief financial officer Somruedee Chaimongko­l, who will succeed Mr Chanin as CEO in April.

“From 2016, we expect to generate [annual] revenues from Hongsa of $50-60 million, which would add to the revenues from the coal-fired power plants in Thailand and China to reach $140 million annually,” added Mr Chanin.

In China, the three plants operated by BIC — Luannan, Zhengding and Zouping — generate 1,200 Mw and recorded higher profits last year due to improved operations.

Chief operating officer Voravudhi Linananda said the company was now developing the $820-million Shanxi Lu Guang plant with a planned installed capacity of 1,200 MW. The plant is a joint venture in which BCI holds 30%, while Shanxi Lu’an Mining Corp Ltd and Gemeng Internatio­nal Energy Co Ltd each hold 35%. Commercial operation is expected to start in mid-2017.

Shanxi Lu Guang will be equipped with a high-efficiency coal boiler that burns lower-grade coal, ultra-supercriti­cal air cooling power generating units, and other environmen­tal protection equipment.

Banpu also plans to continue its regional diversific­ation in power generation and unlock the full value potential of the business through renewable energy including solar, wind and biomass in many countries in Asia Pacific.

“The constructi­on of renewable energy plants requires less cost compared with thermal-coal power plants and require shorter constructi­on time while yielding quicker profits,” said Ms Somruedee.

Mr Chanin said that Banpu had not set any target for renewable energy as a proportion of total generation, adding that reducing carbon emissions of its coal-fired plants by way of new technologi­es was a major focus for now.

He also said that cost and yields remained the main limitation­s on renewable energy. “Although the cost of alternativ­e energy has come down over the years, it is still considered very expensive. There are many limitation­s for alternativ­e energies in terms of usage and practicali­ty.”

For solar energy and hydropower, yields per acre are still minimal and the stability of the inputs is not very reliable. “Coal-fired power plants present a more stable source of energy while keeping your electricit­y bills low,” he added.

To raise funds for its various projects, Banpu plans an initial public offering (IPO) for Banpu Power on the Stock Exchange of Thailand this year or early next year.

Ms Somruedee said that Banpu would continue to hold a controllin­g interest of more than 50% in the power subsidiary after the IPO.

 ??  ?? The 1,878-MW Hongsa power plant in Laos is a joint venture between Banpu, Ratchaburi Electricit­y Generating Holding Co and the Lao government. Commercial operations are scheduled to start in June this year.
The 1,878-MW Hongsa power plant in Laos is a joint venture between Banpu, Ratchaburi Electricit­y Generating Holding Co and the Lao government. Commercial operations are scheduled to start in June this year.