Moragahaka­nda project at a standstill; iron rods cut down to pay workers

- Pix and text by Kanchana Kumara Ariyadasa W. D. Bandaranay­ake.

A section of the multi-billion rupee Moragahaka­nda project has come to a standstill and the iron rods are being cut down to pay the salaries of the employees, a Sri Lanka Mahaweli Authority official said recently.

They said the constructi­on of Elahera ela, which began with the objective of diverting water to the north, has come to a standstill after the private constructi­ng company was removed.

D. M. Wijeratne, project engineer for the Moragahaka­nda scheme's Kalu Ganga project, said project employees were being paid after iron rods installed for the project were cut down.

As the contractor had violated the contract, the company has been removed and they have been instructed to remove all equipment, Mr Wijeratne said.

However their vehicles have been held back by the Authority, he added.

The foundation stone for the project was laid by former President Maithripal­a Sirisena and the constructi­on of the Elahara ela was to be completed last year. The project aims at providing water for 80,000 families in the North Central province, by transferin­g water from the Moragahaka­nda reservoir to the Mahakanada­rawa wewa – a distance of 95 km.

The project has now come to a complete standstill and some workers have not been paid.

An investigat­ion by the Sunday Times revealed that a large number of people were cutting the iron rods off the partially built project.

In some places they have dug trenches to cut the iron rods, causing a risk to wild animals in the area, said the area's wildlife department officer

 ??  ?? Iron rods used for the project were cut down to pay the workers.
Iron rods used for the project were cut down to pay the workers.
 ??  ?? The Elahara ela project was to be completed last year.
The Elahara ela project was to be completed last year.