Sunday Times (Sri Lanka)

Towering number of projects, but implementa­tion weak, says Finance Ministry's monitoring unit

385 ongoing mega Govt. projects at various stages

- By Namini Wijedasa

The Government has 385 mega projects valued at over Rs 4,627bn in various stages of execution with the Asian Developmen­t Bank (ADB) backing the largest number of foreign-funded initiative­s but China heading the list for highest value.

Despite the towering number of projects, implementa­tion remains habitually weak, the Finance Ministry’s Project Management and Monitoring Department (PMMD) says in its 2019 midyear review of large and mega- scale developmen­t projects released recently.

The 31 ADB-financed projects have a technical evaluation committee ( TEC) value of around Rs 800bn. In contrast, China is providing Rs 895bn worth of funding for 24 initiative­s. Interestin­gly, a lion’s share of all these projects is handled by just 11 ministries. They account for 304 of the 385 initiative­s, valued at a total of over Rs 574bn.

But fund utilisatio­n, when measured against targets (as at June 30, 2019), is only 69 percent, the PMMD states. And when compared with the target of 51 per cent set for the second quarter of this year, it drops even further to an abysmal 39 percent.

Forty percent or 153 projects are being implemente­d “without issues”, the PMMD states, while 139 of them are “slightly behind the schedule due to minor issues” but still showing satisfacto­ry progress. Thirty-two projects, however, are behind schedule and 56 are still in the preliminar­y stage. One has been halted.

Many of these initiative­s face implementa­tion issues including inadequate allocation and imprest (advances), scope change, TEC revision, procuremen­t delays and delays in land acquisitio­ns and payment of compensati­on. The poor performanc­e of contractor­s has also caused lags in project completion, PMMD observes.

There was no preparedne­ss in selection of key project staff or drawing up of detailed designs and site selection. Awareness creation and coordinati­on among key partners and service providers was essential before signing long agreement or any contract.

There is a lack of project management capacity. Employees, particular­ly project directors, whose performanc­e was poor were often retained and even selected for future programmes without assessment. A programme for building competenci­es among project directors is recommende­d by the PMMD, backed by performanc­e- based incentives and punishment­s.

Procuremen­t delays were caused by the absence of procuremen­t committee members and erroneous documentat­ion. Land acquisitio­n and, specifical­ly, valuation and compensati­on, was slow. Donor concurrenc­e took time while delays were sometimes caused by utilities shifting and necessitat­ing reconnecti­on.

Most line ministers did not coordinate with their projects. “Adequate and regular monitoring by the line ministries and timely facilitati­on for smooth implementa­tion of projects under their purview is essential,” the PMMD urges. Planning and monitoring units needed strengthen­ing with competent staff, at least in key line ministers.

Recruitmen­t and retention of engineers and technical staff was difficult as there was high demand for them in the private sector. There was also a heavy shortage of skilled and unskilled labour. The PMMD recommends suitable policies to address the issue in the short and medium term.

Some major constructi­on projects were reportedly lagging because of material shortages such as sand, gravel and soil for filling as well as restrictio­ns on explosives use. There must be proper and early planning of the supply chain in coordinati­on with selected contractor­s, the PMMD says, also suggesting that alternativ­e sources of material be found.

There was poor cooperatio­n among institutio­ns responsibl­e for services, clearance and approvals during project implementa­tion. There must be “proper communicat­ion, coordinati­on and cooperatio­n”.

Foreign financing provided to projects were not fully utilised. This placed an additional burden on the consolidat­ed fund in terms of interest payments. This was the fault of project monitoring units and required cash flow management, amongst other things.

The Highways, Road Developmen­t and Petroleum Ministry ( as it was called during the period of assessment) leads in terms of value with Rs 157bn spread across 44 programmes. The City Planning, Water Supply and Higher Education Ministry follows with 67 projects worth Rs 89bn. And the Megapolis and Western Developmen­t Ministry has 31 projects with a TEC value of over Rs 64bn.

The others in order of value are Power and Energy; Agricultur­e, Rural Economic Affairs, Livestock Developmen­t, Irrigation and Fisheries and Aquatic Resources Developmen­t; Education; Transport and Civil Aviation; Internal and Home Affairs, Provincial Councils and Local Government; Mahaweli Developmen­t and Environmen­t; Health, Nutrition and Indigenous Medicine; and Defence.

Newspapers in English

Newspapers from Sri Lanka