Daily Trust

ELECTRICIT­Y

- By Simon Echewofun Sunday

The Niger Delta Power Holding Company (NDPHC) was formed in 2005 as the legal vehicle to implement the National Integrated Power Projects (NIPP) using private sector best business models.

NDPHC was funded from the Excess Crude Account (ECA) of the Federation of Nigeria with equity distributi­on at 18 percent, states at 35 percent and local government­s at 47 percent.

In this analysis, Daily Trust dissects the over N3 trillion investment­s in the NIPPs and their impacts in bridging the power sector infrastruc­ture gap.

This is just as NDPHC plans the NIPP Phase 2 to consolidat­e on its 14 year of infrastruc­ture delivery in the sector.

NIPPs add 4,500MW power to grid in 14 years

Prior to the conception of the NIPP/NDPHC in 2005, Nigeria could barely generate 2,000 megawatts (MW) of electricit­y, but 14 years into its operation, the country now boasts of over 10,00MW installed capacity, with 4,528MW added by the NIPP plants.

Domiciled in the Presidency, NDPHC was funded by ECA with capital funding of about $8.46 billion (about N3.058 trillion) during this period.

The company through the NIPP mandate built 10 gas-fired power stations with a combined installed capacity of 4,528.5MW.

“Today, the NDPHC-built power plants contribute an average of 900MW to the national grid, with about 820MW idle for reasons of evacuation capacity,” the projects’ brief obtained yesterday stated.

During the Phase 1 of the NIPP, the company built several gas pipelines and its accessorie­s to deliver natural gas to the 10 NIPP power plants.

Expanding transmissi­on, distributi­on networks

As at 2005, Nigeria had 4,495 kilometre (km) transmissi­on line capacity on 330 kilovolt (kV) lines. In terms of transforme­r capacity, the country had 5,300 mega volt ampere (MVA) capacity on the 330/132kV transmissi­on band. It has another 5,700MVA capacity for 132/33kV transmissi­on band.

Prior to the delivery of the NIPP projects, Nigeria had 8,148MVA distributi­on transforme­r capacity across the 33/11kV substation­s. At a step down level of 33kV, 11/0.41kV substation, it had 32,000MVA power supply capacity.

Comparativ­ely, 14 years into the NIPPs implementa­tion, NDPHC has raised bulk electricit­y transmissi­on capacity on 330kV lines to 6,932km, signifying 46 percent increase. The transforme­r capacity on this 330/132Kv transmissi­on band rose to 11,590MVA, showing a 93 percent increase from the 5,300MVA before the period.

The transforme­r capacity on 132/33kV transmissi­on band also rose to 11,118MVA, higher by 42 percent. At the power distributi­on level, the 33/11kV substation­s rose by 43% capacity to 11,649MVA; 33kV and 11/0.41kV substation­s were increased by 163% to 84,170MVA capacity.

Further breakdown shows NIPP added 5,590MVA of 330/132kV transforme­r capacity; 3,313MVA of 132/33kV capacity; 2,194km of 330kV lines; 809km of 132KV lines; 10 330kV substation­s; and seven 132kV substation­s.

NDPHC also expanded 36 existing 330kV and 132kV substation­s. It executed 296 distributi­on projects nationwide, which brought in 3,540MVA injection substation capacity. Among other power distributi­on projects are the constructi­on of 2,600km of 11kV lines for High Voltage Distributi­on System (HVDS), 25,900 Completely Self Protected (CSP) transforme­rs and 1,700km of 33kV lines.

With the delivery of critical projects in power transmissi­on and gas-to-power generation, NDPHC said new challenges emerged. The Transmissi­on Company of Nigeria (TCN) has a wheeling capacity of about 8,100 megawatts (MW) but the load absorption capacity of the 11 Distributi­on Companies (DisCos) is only about 68 percent (about 4,600MW) of the TCN wheeling capacity.

This inadequacy of the distributi­on network leaves between 2,500MW to 3,000MW stranded generation capacity and the results are: shaky transmissi­on grid integrity, frequency and load control issues, load rejection by DisCos poor infrastruc­ture among

Newspapers in English

Newspapers from Nigeria