The Timaru Herald

Church repair bill goes a bit higher

- Lauren Pattemore JOHN BISSET/STUFF

The cost to earthquake strengthen Timaru’s St Mary’s Church has increased by $20,000 and the work has been extended by eight weeks after it was discovered the building’s steel supports needed to be replaced.

The 136-year-old church has been undergoing earthquake repairs for almost a decade, and its tower has been encased in scaffoldin­g for almost two years as strengthen­ing work took place on the 32-metre tower.

However, the church’s vicar warden Murray Gibson said yesterday the steel supports, in the tower and not included in the initial project timeline, also needed to be replaced, which happened this week.

After starting the project of replacing the church’s four pinnacles, which were ordered to be removed after one moved during the 2010 earthquake, they found the old reinforcem­ents also needed to be replaced, he said.

‘‘The steel has been weathered too much for new pinnacles to go on top.’’

This has added another eight weeks to the project and $20,000 to the bill, at a time when money is becoming tight for the congregati­on, meaning another way needed to be found to pay for the project costs.

‘‘We’ve just about exhausted our reserves. We have to pay quite a large excess,’’ Gibson said.

Not being a large congregati­on, it meant the church would need to look at other ways of raising money, he said.

‘‘We’ve got some ideas but nothing concrete.’’

While the project had taken ‘‘a long time’’, Gibson said he was excited for the church to be complete, which he believes will be next April.

‘‘It’s going to be magnificen­t. They [the pinnacles] are going to be as good if not better than before.’’

The pinnacles were made by J Tait Stonemason­ry Contractor­s in Christchur­ch and the constructi­on and strengthen­ing was completed by South Canterbury companies.

Gibson said he was ‘‘delighted that local people were doing the constructi­on’’ and Timaru Constructi­on had done the job.

He said the replacemen­t of the pinnacles, weighing two tonnes and 2m high, was ‘‘seven to eight years in the making’’ when things such as acquiring resource consents and the carving of the pinnacles, were taken into considerat­ion.

 ?? ?? Strengthen­ing of the St Mary’s Church tower will add eight weeks and $20,000 to the project, which is scheduled to end next April.
Strengthen­ing of the St Mary’s Church tower will add eight weeks and $20,000 to the project, which is scheduled to end next April.

Newspapers in English

Newspapers from New Zealand