Benito Juarez underpass is thrown open to public

- AGE CORRESPOND­ENT NEW DELHI, JULY 2

Deputy chief minister Manish Sisodia, on Saturday, inaugurate­d the Benito Juarez underpass here that will help commuters travelling from Delhi Airport to Gurgaon bypass traffic bottleneck­s and save time.

Officials said the 1.2 kmlong Y-shaped underpass will also improve connectivi­ty between the airport, Chanakyapu­ri, and AIIMS.

“With the launch of the 1.2 kilometre Y-shaped underpass on Benito Juarez Marg, lakhs of commuters between Delhi and Gurgaon will no longer have to deal with traffic jams on a daily basis.

“Considerin­g the economic value of time, the underpass will save `18 crore for Delhiites. Many congratula­tions everyone!” Mr Sisodia said in a tweet in Hindi.

The underpass saw the light of the day after missing eight deadlines.

Commuters travelling to AIIMS, Chanakyapu­ri, and Yashwant Place from the airport and Gurgaon will now be able to bypass traffic bottleneck­s at the Outer Ring Road, Dhaula Kuan, and Rao Tula Ram Marg by using this facility, officials said.

The underpass starts near Delhi University’s Sri Venkateshw­ara College and goes beneath the South Campus Metro station on to the Ring Road. One of its arms opens on the San Martin Road while the other one on the Ring Road towards Moti Bagh, they said.

The newly constructe­d underpass is likely to save around 8-10 minutes for commuters.

According to officials, the project included constructi­on of a three-lane underpass, near Venkateshw­ara College in South Delhi connecting Benito Juarez Road with San Martin Road.

The dual access one-way underpass starts near

Springdale­s School on Benito Juarez Road and passes under the South Campus Metro station on the Ring Road, they said.

One arm of the underpass goes to San Martin Road while the other will open on Ring Road towards Moti Bagh, they said.

The work on the project had started in April 2015 and was to be completed in October 2017. It missed several deadlines due to slow pace of work owing to the coronaviru­s-induced lockdown. PWD officials said the project was initially delayed due to shifting of utilities and the complex nature of constructi­on work.

Later, it was delayed by the constructi­on bans imposed due to Covid lockdown, labour shortage, and pollution restrictio­ns, officials said.

The official said the latest deadline was May 2022. The facility aims to reduce travel time from the airport to Central Delhi and AIIMS by 8-10 minutes.

 ?? — PTI ?? Delhi deputy CM Manish Sisodia at the inaugurati­on of an underpass on the Benito Juarez Marg in New Delhi on Saturday.
— PTI Delhi deputy CM Manish Sisodia at the inaugurati­on of an underpass on the Benito Juarez Marg in New Delhi on Saturday.