HITS WORK AT JUNCTIONS

LACK OF CO-ORDINATION

- DC CORRESPOND­ENT

Junction, Paradise, Kukatpally, Suchitra, Ramanthapu­r and Balanagar junction.

A senior GHMC official told this newspaper on condition of anonymity that multiple factors have contribute­d to the delay of the junction improvemen­t plan. He said that the staff crunch is one of the key issues as several of them were deputed to supervise the SRDP. The corp. itself has partly developed a few junctions since there were no takers for the project. He said that it would not finalise tenders as of now and citizens will have to bear the inconvenie­nce till January 2019 from when work will begin. Shifting utility infrastruc­ture and acquiring land are affecting in the junction improvemen­t plan. GHMC officials claimed that the corporatio­n had not acquired a single property or land since two years.

A GHMC official claimed that the lack of co-ordination between town planning and electricit­y department­s had been delaying the plan. He said that the corporatio­n got consent from a few property owners but electricit­y officials did not know about shifting of electricit­y poles to facilitate road widening.

The official claimed that the town planning wing did not even acquired a single chunk of land and single property since a year without which project could not be progressed.

LACK OF co-ordination between town planning and electricit­y department­s had been delaying the plan as per an official.