Toronto Star

Brampton didn’t ‘act reasonably’ in lawsuit

Pretrial ruling points out city took more than four years to file motion, caused delay

- SAN GREWAL URBAN AFFAIRS REPORTER

In a pretrial ruling for a lawsuit that could cost Brampton taxpayers millions of dollars, a judge says the city has “failed to act reasonably,” has caused “unexplaine­d delay” and has incurred costs for a motion to dismiss the case even when its strategy was “doomed to failure.”

The recent ruling orders the City of Brampton to pay $418,000 in legal and other costs for its own failed motion, after abandoning its attempt to get the case thrown out. It is the latest setback for the city in the $28.5-million lawsuit filed against it by a local builder disqualifi­ed from bidding on a half-billion dollar downtown redevelopm­ent project in 2010.

In awarding costs to Inzola Group Ltd., Ontario Superior Court Justice Peter Daley stated in his June 20 decision that, “The interests of the administra­tion of justice were certainly not met as a result of the unexplaine­d delay in the bringing of the summary judgment motion” to have the lawsuit dismissed.

Daley said “no reasonable explanatio­n has been offered by the defendant as to why it waited four-and-ahalf years from the commenceme­nt of this action to bring the summary judgment motion, and this delay ultimately pushed the scheduling of the trial of this action out an additional year.”

Asked to respond to the Superior Court decision, City of Brampton spokespers­on Erin O’Hoski said in an email Thursday, “The city is moving as quickly as possible towards trial, which has been scheduled for eight weeks commencing May 7, 2018, at which all of the relevant evidence will be considered by the court.”

The city did not respond to Daley’s finding that it offered “no reasonable explanatio­n” as to why it waited four-and-a-half years to file its failed dismissal motion.

Daley also pointed out that the city was late in disclosing more than 4,500 documents requested by the plaintiff after filing its lawsuit.

Inzola’s statement of claim alleges that it was unfairly disqualifi­ed from the downtown project’s bidding process because senior staff and former mayor Susan Fennell were biased against the company. The city denies all the lawsuit’s allegation­s.

After the dismissal motion was filed last year, Inzola deposed former Brampton chief administra­tive officer John Corbett, who had served on the selection committee for the developmen­t deal under his role prior to getting the CAO job.

He testified that Fennell had a “preferred” bidder for the deal and that the selection committee was biased against Inzola.

Daley wrote in his cost decision that the city’s lawyers “accepted” that Corbett’s evidence for the motion “seriously impugned the credibilit­y of other senior city staff.”

Daley added that the city’s strategy to get the case thrown out was “doomed to failure” because of Corbett’s evidence.

He said the city offered “no evidence . . . as to the reasons for the decision to abandon” its dismissal motion, but that Corbett’s testimony appeared to “be problemati­c for the defendant in terms of achieving any success on this summary judgment motion.”

Daley stated that the plaintiff, while arguing for its costs to fight the failed motion, suggested that when the city launched its strategy, both the city and its legal counsel should have known the position of Brampton’s former CAO, who was directly involved in the selection process for the developmen­t project.

There are no allegation­s in the lawsuit against the winning bidder.

Daley wrote that the plaintiff argued that because of Corbett’s role and direct tie to the city, it should have known his position “long before this cross-examinatio­n in September 2016.”

Additional costs weren’t awarded for this, but the decision does include extra costs because the city didn’t abandon its motion right after Cor- bett’s testimony, instead choosing to allow two more months of cross-examinatio­ns, incurring more costs when it should have known “the motion should be abandoned,” Daley wrote.

Daley said, “I have concluded that the defendant acted unreasonab­ly in pursuing the motion after the evidence from Mr. Corbett was clearly in the record in September 2016.” When asked to respond to the court’s finding that it acted “unreasonab­ly,” O’Hoski said, “Judge Daley found that the city was reasonable in filing the motion and did not act in bad faith when it withdrew.”

Asked who will pay the $418,000 awarded by the court, the city said those costs will be paid by “the city’s insurers and not by Brampton taxpayers.”

The city did not respond, however, when asked if it has guaranteed insurance to cover the $28.5 million being sought in the lawsuit if it loses at trial and additional legal costs over almost eight years by the time the trial concludes.

 ?? CHRIS SO/TORONTO STAR FILE PHOTO ?? The judge wrote that Brampton’s strategy was “doomed to failure” due to former CAO John Corbett’s testimony.
CHRIS SO/TORONTO STAR FILE PHOTO The judge wrote that Brampton’s strategy was “doomed to failure” due to former CAO John Corbett’s testimony.

Newspapers in English

Newspapers from Canada