The Press

Public forks out more for library

- NICK TRUEBRIDGE

The public will fork out millions of dollars more than once thought to build Christchur­ch’s new central library, partly due to ‘‘expanded expectatio­ns’’ for the new facility.

The Christchur­ch City Council’s contributi­ons to the building – which is nearing completion on the corner of Cathedral Square and Gloucester St – have increased by millions of dollars over the past five years. It puts some of the increased spend down to taking inspiratio­n from libraries in northern Europe, Canada and the United States.

Meanwhile, the opening of the library, officially named Tu¯ ranga, has been delayed due to problems getting materials from overseas.

Figures supplied by the Crown and council this week suggest the total spend will be just less than

$100 million, about $10m more than the 2013 forecast of $89.36m.

The council’s head of vertical capital delivery and profession­al services, Liam Nolan, said its original estimated contributi­on to the library was $60m. The 2013 projection, outlined in the Crown-council cost-sharing agreement (CSA), did not include the cost of decontamin­ating and backfillin­g the site.

‘‘This was later increased to

$75m to meet the expanded expectatio­ns of the project, and then to $85m when the council agreed to underwrite the required philanthro­pic capital,’’ Nolan said.

‘‘Expanded expectatio­ns’’, Nolan said, came about after the project requiremen­ts were compared to similar facilities, which ‘‘identified a need for more funding’’.

‘‘The council, together with its architectu­ral partners, looked closely at best-practice internatio­nal examples of modern public libraries in the US, Canada and Northern Europe, including

Dokk1, Denmark; Halifax Central Library, Nova Scotia; the Library of Birmingham, England; and the Seattle Central Library,’’ he said.

As a result, increased floor space was introduced to ‘‘maximise the amount of publicly available and multi-purpose space within the building’’.

Sums of $5.5m and $2.2m were added to the council contributi­on to cover the cost of the land and land remediatio­n, bringing its budget to $92.7m, Nolan said.

Anne Shaw, director the Department of the Prime Minister and Cabinet’s Greater Christchur­ch Group, said the Crown had contribute­d $12.7m. The money had gone into land acquisitio­ns and demolition­s for the new library site.

‘‘In a separate transactio­n, the council reimbursed the Crown $5.5m – being the amount the Crown paid for the old central library land, now part of the Christchur­ch convention centre precinct,’’ Shaw said.

The library had been scheduled to open in mid-2018, but Nolan said it would now open in the third quarter of this year.

‘‘The duration of the constructi­on works has been extended by issues affecting the supply of some of the materials that had to be procured from overseas,’’ he said.

‘‘In addition, the council has chosen to incorporat­e additional external street works into the scope of the project which have, in turn, also extended the duration of the constructi­on works.

‘‘These will involve the upgrading of sections of Gloucester and Colombo streets, and the repair of sections of the north-eastern corner of Cathedral Square.’’

Shaw clarified why the Crown had not contribute­d $19.363m to the library project, which was its earmarked contributi­on in the CSA.

‘‘Like any cost estimates in the CSA, the figure of $19.363m was an estimate, as at mid-2013, of how much it would cost for the Crown to purchase the land,’’ Shaw said.

‘‘However, being subject to ongoing negotiatio­ns, in the end the actual costs for land acquisitio­n were less.’’

The council, as the lead organisati­on on the project, made decisions independen­tly from the Crown on what facilities would be built.

The Crown had ‘‘no responsibi­lity for the cost of delivering those facilities’’, Shaw said.

‘‘Each project included in the CSA agreed in July 2013 outlined responsibi­lities for funding and delivering the projects, and estimates of costs associated with those responsibi­lities.

‘‘These estimates were almost always subject to further work or negotiatio­n, and there has been variation across all the projects in the actual costs of land acquisitio­n, project delivery and other responsibi­lities.

‘‘Under the CSA in relation to the central library, the Christchur­ch City Council leads the project and is responsibl­e for delivering the facilities, while the Crown is responsibl­e for providing land.

‘‘The Crown has met its obligation­s under the CSA by providing the land for the project,’’ she said.

‘‘The duration of the constructi­on works has been extended by issues affecting the supply of some of the materials that had to be procured from overseas.’’

Anne Shaw, director the Department of the Prime Minister and Cabinet’s Greater Christchur­ch Group

 ??  ??
 ?? PHOTOS LEFT: STACY SQUIRES/STUFF ?? Christchur­ch’s new central library, which is set to open midyear, will feature New Zealand’s biggest interactiv­e touch wall.
PHOTOS LEFT: STACY SQUIRES/STUFF Christchur­ch’s new central library, which is set to open midyear, will feature New Zealand’s biggest interactiv­e touch wall.
 ??  ??

Newspapers in English

Newspapers from New Zealand